- Welcome
- Our School
- Our Program
- Admissions
- Giving
- Summer Program
Page 1 of 1
Now viewing articles posted in 2026.
February 20 Update
February 23rd, 2026
This past week's updates from our construction team:Roof conduit routing is nearly complete.Window wraps and install is nearly complete.WRB install at the at the literacy room elevations is complete.Exterior insulation install is in progress, staring at the NW corner of the building.Wood framing at ...
February 2 Update
February 2nd, 2026
Another busy couple of weeks on our construction site! Here are updates from the team:The TPO roof above the art, kiln, conference, and storage rooms is complete.The wood framing for the roof above the literacy room is complete.Window wraps and install is progressing through the south façade.Girt ...
January 16 Update
January 20th, 2026
It's been a busy two weeks! Recent updates include:installation of vapor barrier for the metal roofhot rubber install, in progressroof conduit install at the low roof above the art, conference, and storage rooms is completewood framing (ongoing)pouring of concrete curbs rough-ins ongoing in areas,...
January 2 Update
January 7th, 2026
At this stage, visible progress on the expansion increases each week. Most recently, the team: - installed metal decking rebar and structural steel in certain areas; - installed scaffolding in the NW corner of the building; - ongoing rough-in and wood framing, as well as fire sprinkler rough-in...
Page 1 of 1




