 Here are this week’s activities:

  • The remaining hardie siding above the entry canopy was painted this week
  • Downspout install is ongoing
  • Level 2 Terrace concrete paver install is in progress
  • Level 2 Plumbing trim install is nearly complete
  • Level 2 flooring install is completed by the elevator vestibule and Small Group area
  • Level 2 interior glazing install started this week
  • Level 2 bath hardware install is in progress
  • Level 1B & 1A interior glazing install is progressing
  • Level 1B & 1A drywall punch is ongoing
  • Level 1B & 1A electrical wall trim install is progressing
  • Level 1B & 1A bath hardware accessory install is ongoing
  • Level 1A light reflectors were install in the MPR and Art rooms
  • Finish coat sealer application in the literacy room GLB stair treads started today
  • Asphalt paving at the north parking lot was completed this week
  • The trench drain at the north parking lot entrance was poured this week
  • Playground install at the south site is ongoing
  • Site fencing at the SW corner and shoring wall is nearly complete
  • The fence posts for the SE site fencing were installed today.
  • Site grading and excavation for the south retaining wall is progressing.

Next week we will be pouring the footing for the south concrete retaining wall, installing visual display units, & installing the acoustic wall panels in the MPR room.