June 19 Update
June 19th, 2026
Here are this week’s activities:
- The remaining hardie siding above the entry canopy was painted this week
- Downspout install is ongoing
- Level 2 Terrace concrete paver install is in progress
- Level 2 Plumbing trim install is nearly complete
- Level 2 flooring install is completed by the elevator vestibule and Small Group area
- Level 2 interior glazing install started this week
- Level 2 bath hardware install is in progress
- Level 1B & 1A interior glazing install is progressing
- Level 1B & 1A drywall punch is ongoing
- Level 1B & 1A electrical wall trim install is progressing
- Level 1B & 1A bath hardware accessory install is ongoing
- Level 1A light reflectors were install in the MPR and Art rooms
- Finish coat sealer application in the literacy room GLB stair treads started today
- Asphalt paving at the north parking lot was completed this week
- The trench drain at the north parking lot entrance was poured this week
- Playground install at the south site is ongoing
- Site fencing at the SW corner and shoring wall is nearly complete
- The fence posts for the SE site fencing were installed today.
- Site grading and excavation for the south retaining wall is progressing.
Next week we will be pouring the footing for the south concrete retaining wall, installing visual display units, & installing the acoustic wall panels in the MPR room.