1Page 1 of 1

Now viewing articles posted in 2025.

  • October 6 Update

    October 6th, 2025


    October 6 Update
    Last week, our construction team: - finished pouring the last of the larger retaining and brace frame walls; - began installing waterproofing along certain retaining walls, as well as footing drains; - completed vapor barrier and wire mesh install. This week:  - Slab pour! - Waterproofing the...

    Read More

  • September 29 Update

    September 29th, 2025


    September 29 Update
    Last week, our construction team:- poured the remaining concrete walls in the SW corner of the project and prepped them for waterproofing, - installed waterproofing behind the tall walls at the SW corner,  - poured more footings.  This week: The teams plans to pour all of the walls within a de...

    Read More

  • September 22 Update

    September 22nd, 2025


    September 22 Update
    Last week, our construction team:- stripped all of the walls and footings from the previous week's pour;- backfilled some walls, allowing subcontractors to do rough-in work;- installed below-grade damp-proofing and rigid insulation for perimeter walls in certain areas;- and the electrical vault has...

    Read More

  • September 15 Update

    September 15th, 2025


    September 15 Update
    Last week, our construction team: - had our first mobile crane onsite, - stripped walls in the north corner, - and continued work forming and pouring footings in different parts of the site   This week: Continuing work on footings, and starting form-work for stem walls. 

    Read More

  • September 5 Update

    September 8th, 2025


    September 5 Update
    This week, our construction team:began forming some walls in the SW cornercontinued to move forward with the north side of the site, forming walls and pouring them on Fridaybegan laying out deep brace frame footing in several site areascompleted digging pad footing in other areas.Next week: A concre...

    Read More

  • August 29 Update

    September 2nd, 2025


    August 29 Update
    This week, our construction team:completed the backfill for the last catch basin on N 150th and Burke Ave,poured more concrete footings,ran the deep underground storm piping under the building footprint,completed the form work for several concrete walls.  Next week: Rebar install for walls begins...

    Read More

  • August 22 Update

    August 25th, 2025


    August 22 Update
    From W. G. Clark Construction:This week, the team:Poured the first concrete of the project! Basement and elevator pit footings are poured, and we laid out the level-two footings. Finished up the last of the catch basins on N 150th St and laying pipe for the sewer connection on the west side of the ...

    Read More

  • August 15 Update

    August 18th, 2025


    August 15 Update
    From W. G. Clark Construction:This week, our team:Continued on more catch basin and storm pipe install in the right of way.Completed the digging and layout for the basement footings. Next week we start concrete!Finished running the sewer piping into the building footprint.Looking ahead to next week:...

    Read More

1Page 1 of 1