1Page 1 of 1

Now viewing articles posted in 2026.

  • May 15 Update

    May 18th, 2026


    May 15 Update
    The exterior continues to progress, but there's so much happening inside as well! Updates from our team include: The metal roofing and solatube skylight install for covered classroom is complete. Siding progressing around the site: install, painting. Conduit routing and insulation install ...

    Read More

  • May 1 Update

    May 4th, 2026


    May 1 Update
    It's amazing to see the building these days!  Updates from our contractors for this past week:Siding along the south elevation is installed and painted up to the precast stair locationExterior aluminum sliding doors were delivered and installed.Storage room walls insulatedLevel 2 plumbing trim ins...

    Read More

  • April 17 Update

    April 20th, 2026


    April 17 Update
    Looking at the building from the outside, progress seems to be accelerating week to week—and there's been so much hidden progress on the inside, too!    This past week, the construction team reports: Metal roofing panel install is progressing All rooftop HVAC units have b...

    Read More

  • March 27 Update

    March 30th, 2026


    March 27 Update
    We have siding! This past week, our construction team shared: Roof insulation and vapor barrier install for the metal roof completed Painting begun on lap siding at NW corner Hot rubber detailing nearly completed on a terrace Elevator install begun East side concrete retaining walls...

    Read More

  • March 6 Update

    March 9th, 2026


    March 6 Update
    Progressing on the Exterior and Interior Too   So much happening on the site! Our construction team has shared these recent updates: Roof conduit routing is nearing completion Window install is complete, and we have passed window test inspections Ongoing install of metal flash...

    Read More

  • February 20 Update

    February 23rd, 2026


    February 20 Update
    This past week's updates from our construction team:Roof conduit routing is nearly complete.Window wraps and install is nearly complete.WRB install at the at the literacy room elevations is complete.Exterior insulation install is in progress, staring at the NW corner of the building.Wood framing at ...

    Read More

  • February 2 Update

    February 2nd, 2026


    February 2 Update
    Another busy couple of weeks on our construction site! Here are updates from the team:The TPO roof above the art, kiln, conference, and storage rooms is complete.The wood framing for the roof above the literacy room is complete.Window wraps and install is progressing through the south façade.Girt ...

    Read More

  • January 16 Update

    January 20th, 2026


    January 16 Update
    It's been a busy two weeks! Recent updates include:installation of vapor barrier for the metal roofhot rubber install, in progressroof conduit install at the low roof above the art, conference, and storage rooms is completewood framing (ongoing)pouring of concrete curbs rough-ins ongoing in areas,...

    Read More

  • January 2 Update

    January 7th, 2026


    January 2 Update
    At this stage, visible progress on the expansion increases each week. Most recently, the team: - installed metal decking rebar and structural steel in certain areas; - installed scaffolding in the NW corner of the building; - ongoing rough-in and wood framing, as well as fire sprinkler rough-in...

    Read More

1Page 1 of 1