May 1 Update

May 4th, 2026


It's amazing to see the building these days! 
 
Updates from our contractors for this past week:
  • Siding along the south elevation is installed and painted up to the precast stair location
  • Exterior aluminum sliding doors were delivered and installed.
  • Storage room walls insulated
  • Level 2 plumbing trim install ongoing 
  • Level 2 flooring install and tile prep for bathrooms complete
  • Metal roofing panel nearly complete 
  • Level 1A ceiling tile framing at the entry vestibule and reception area complete
  • Level 1A light install prep is ongoing and fixtures installed 
  • The Literacy Room concrete ramp was poured this week, and exposed ceiling and trusses were painted
  • Entry canopy wood framing is nearly complete
  • The concrete sidewalks on Burke Ave were poured this week
  • The south site playground area was backfilled and graded this week
  • The FDC and water line were stubbed into the building and inspected