May 1 Update
May 4th, 2026
It's amazing to see the building these days!
Updates from our contractors for this past week:
- Siding along the south elevation is installed and painted up to the precast stair location
- Exterior aluminum sliding doors were delivered and installed.
- Storage room walls insulated
- Level 2 plumbing trim install ongoing
- Level 2 flooring install and tile prep for bathrooms complete
- Metal roofing panel nearly complete
- Level 1A ceiling tile framing at the entry vestibule and reception area complete
- Level 1A light install prep is ongoing and fixtures installed
- The Literacy Room concrete ramp was poured this week, and exposed ceiling and trusses were painted
- Entry canopy wood framing is nearly complete
- The concrete sidewalks on Burke Ave were poured this week
- The south site playground area was backfilled and graded this week
- The FDC and water line were stubbed into the building and inspected