Here are updates from the team:
January 30 Update
February 2nd, 2026
Another busy couple of weeks on our construction site!
Here are updates from the team:
- The TPO roof above the art, kiln, conference, and storage rooms is complete.
- The wood framing for the roof above the literacy room is complete.
- Window wraps and install is progressing through the south façade.
- Girt installation for exterior insulation is in progress on the west and north elevations.
- Parapet wall termination on parts of the south facade of the building is complete.
- Elsewhere in various sectors of the site, exterior wall framing and rough-in continues.
- Excavation and utility work for the SCL vault on the east side of the building is in progress