January 2 Update

January 7th, 2026


At this stage, visible progress on the expansion increases each week. Most recently, the team:

- installed metal decking rebar and structural steel in certain areas;
- installed scaffolding in the NW corner of the building;
- ongoing rough-in and wood framing, as well as fire sprinkler rough-in, in other areas;
- window wraps are in progress in preparation for window install, coming soon.