This past week's updates from our construction team:
- Roof conduit routing is nearly complete.
- Window wraps and install is nearly complete.
- WRB install at the at the literacy room elevations is complete.
- Exterior insulation install is in progress, staring at the NW corner of the building.
- Wood framing at the 220 Mechanical Room is in progress.
- Hot rubber install on the L2 terrace between GL 1-5 started today (Friday).
- Rough-in progressing in various areas.
- Hollow-metal frame install on Slab 1A has started.
- Site concrete footing layout and excavation has started.