April 17 Update
April 20th, 2026
Looking at the building from the outside, progress seems to be accelerating week to week—and there's been so much hidden progress on the inside, too!
This past week, the construction team reports:
- Metal roofing panel install is progressing
- All rooftop HVAC units have been set
- Siding install along the east and south facades is in progress
- Hardie siding along the NW façade has been painted (down to the canopy line) and scaffolding has been dismantled
- The floating concrete curbs at the L2 Terrace have been poured this week
- Level 2 acoustical ceiling grid framing is in progress
- In various sections of the site, plumbing trim install, finish carpentry, duct work, and wood door & frame installs are in progress
- Elevator install is nearly complete and in preparation for final adjustments
- Demo and grading for curbs and sidewalk down Burke Avenue in progress
- Survey for remaining utilities in the north parking lot and on the south side of the site is complete