Now viewing articles posted in September 2025.

  • September 29 Update

    September 29th, 2025


    September 29 Update
    Last week, our construction team:- poured the remaining concrete walls in the SW corner of the project and prepped them for waterproofing, - installed waterproofing behind the tall walls at the SW corner,  - poured more footings.  This week: The teams plans to pour all of the walls within a de...

    Read More

  • September 22 Update

    September 22nd, 2025


    September 22 Update
    Last week, our construction team:- stripped all of the walls and footings from the previous week's pour;- backfilled some walls, allowing subcontractors to do rough-in work;- installed below-grade damp-proofing and rigid insulation for perimeter walls in certain areas;- and the electrical vault has...

    Read More

  • September 15 Update

    September 15th, 2025


    September 15 Update
    Last week, our construction team: - had our first mobile crane onsite, - stripped walls in the north corner, - and continued work forming and pouring footings in different parts of the site   This week: Continuing work on footings, and starting form-work for stem walls. 

    Read More

  • September 5 Update

    September 8th, 2025


    September 5 Update
    This week, our construction team:began forming some walls in the SW cornercontinued to move forward with the north side of the site, forming walls and pouring them on Fridaybegan laying out deep brace frame footing in several site areascompleted digging pad footing in other areas.Next week: A concre...

    Read More

  • August 29 Update

    September 2nd, 2025


    August 29 Update
    This week, our construction team:completed the backfill for the last catch basin on N 150th and Burke Ave,poured more concrete footings,ran the deep underground storm piping under the building footprint,completed the form work for several concrete walls.  Next week: Rebar install for walls begins...

    Read More