October 20 Update

October 20th, 2025


Last week our construction team:

  • Finished pouring the last of the building's footings and stem walls.
  • Prepped for slabs in certain quadrants with backfill, damp proofing, and reinforcing.
  • Set and backfilled two Seattle City Light vaults.
  • Began setting steel columns.

 

This week, we had a big concrete pour today (Monday) to pour slabs in the SW quadrant. The team will continue to set steel columns and beams during the week.