October 14 Update
October 14th, 2025
Last week, our construction team:
- poured the first slab of the entire project!
- formed the last of the future building's footings, ready to be poured
- completed more damp-proofing and waterproofing
This week:
- We'll have a mobile crane onsite Monday and Tuesday for steel install
- Concrete pours are planned for Monday and Wednesday, completing all concrete footings and walls for the building's structure.