October 6 Update

October 6th, 2025


Last week, our construction team:
- finished pouring the last of the larger retaining and brace frame walls;
- began installing waterproofing along certain retaining walls, as well as footing drains;
- completed vapor barrier and wire mesh install. 

This week: 
- Slab pour!
- Waterproofing the poured walls, which lets us prepare for backfill.