September 22 Update
September 22nd, 2025
Last week, our construction team:
- stripped all of the walls and footings from the previous week's pour;
- backfilled some walls, allowing subcontractors to do rough-in work;
- installed below-grade damp-proofing and rigid insulation for perimeter walls in certain areas;
- and the electrical vault has arrived! (see photo)
This week: Plan to pour formed walls on Monday with a foundation pour scheduled for Wednesday. The team will also continue to dig and form the last of the footings.