1Page 1 of 1

Now viewing articles posted in May 2026.

  • May 15 Update

    May 18th, 2026


    May 15 Update
    The exterior continues to progress, but there's so much happening inside as well! Updates from our team include: The metal roofing and solatube skylight install for covered classroom is complete. Siding progressing around the site: install, painting. Conduit routing and insulation install ...

    Read More

  • May 1 Update

    May 4th, 2026


    May 1 Update
    It's amazing to see the building these days!  Updates from our contractors for this past week:Siding along the south elevation is installed and painted up to the precast stair locationExterior aluminum sliding doors were delivered and installed.Storage room walls insulatedLevel 2 plumbing trim ins...

    Read More

1Page 1 of 1