November 3 Update
November 3rd, 2025
Last week, our construction team:
- completed pouring on-grade concrete slabs for the project
- continued structural steel framing
- worked on wood framing installs
Next week, they will be continuing wood framing and steel install as well as trenching for primary power. Look for a steel delivery at the end of next week.