September 22 Update

September 22nd, 2025


Last week, our construction team:

- stripped all of the walls and footings from the previous week's pour;

- backfilled some walls, allowing subcontractors to do rough-in work;

- installed below-grade damp-proofing and rigid insulation for perimeter walls in certain areas;

- and the electrical vault has arrived! (see photo)

This week: Plan to pour formed walls on Monday with a foundation pour scheduled for Wednesday. The team will also continue to dig and form the last of the footings.