Now viewing articles posted in February 2026.

  • February 20 Update

    February 23rd, 2026


    February 20 Update
    This past week's updates from our construction team:Roof conduit routing is nearly complete.Window wraps and install is nearly complete.WRB install at the at the literacy room elevations is complete.Exterior insulation install is in progress, staring at the NW corner of the building.Wood framing at ...

    Read More

  • February 2 Update

    February 2nd, 2026


    February 2 Update
    Another busy couple of weeks on our construction site! Here are updates from the team:The TPO roof above the art, kiln, conference, and storage rooms is complete.The wood framing for the roof above the literacy room is complete.Window wraps and install is progressing through the south façade.Girt ...

    Read More