1Page 1 of 1

Now viewing articles posted in February 2026.

  • January 30 Update

    February 2nd, 2026


    January 30 Update
    Another busy couple of weeks on our construction site! Here are updates from the team:The TPO roof above the art, kiln, conference, and storage rooms is complete.The wood framing for the roof above the literacy room is complete.Window wraps and install is progressing through the south façade.Girt ...

    Read More

1Page 1 of 1