October 6 Update
October 6th, 2025
Last week, our construction team: - finished pouring the last of the larger retaining and brace frame walls; - began installing waterproofing along certain retaining walls, as well as footing drains; - completed vapor barrier and wire mesh install. This week: - Slab pour! - Waterproofing the...