January 16 Update
January 20th, 2026
It's been a busy two weeks! Recent updates include:installation of vapor barrier for the metal roofhot rubber install, in progressroof conduit install at the low roof above the art, conference, and storage rooms is completewood framing (ongoing)pouring of concrete curbs rough-ins ongoing in areas,...
January 2 Update
January 7th, 2026
At this stage, visible progress on the expansion increases each week. Most recently, the team: - installed metal decking rebar and structural steel in certain areas; - installed scaffolding in the NW corner of the building; - ongoing rough-in and wood framing, as well as fire sprinkler rough-in...