June 19 Update
June 19th, 2026
Here are this week’s activities:The remaining hardie siding above the entry canopy was painted this weekDownspout install is ongoingLevel 2 Terrace concrete paver install is in progressLevel 2 Plumbing trim install is nearly completeLevel 2 flooring install is completed by the elevator vestibule...