- Welcome
- Our School
- Our Program
- Admissions
- Giving
- Summer Program
Page 1 of 1
Now viewing articles posted in October 2025.
October 20 Update
October 20th, 2025
Last week our construction team:Finished pouring the last of the building's footings and stem walls.Prepped for slabs in certain quadrants with backfill, damp proofing, and reinforcing.Set and backfilled two Seattle City Light vaults.Began setting steel columns. This week, we had a big concrete pou...
October 14 Update
October 14th, 2025
Last week, our construction team:- poured the first slab of the entire project!- formed the last of the future building's footings, ready to be poured- completed more damp-proofing and waterproofing This week: - We'll have a mobile crane onsite Monday and Tuesday for steel install- Concrete ...
October 6 Update
October 6th, 2025
Last week, our construction team: - finished pouring the last of the larger retaining and brace frame walls; - began installing waterproofing along certain retaining walls, as well as footing drains; - completed vapor barrier and wire mesh install. This week: - Slab pour! - Waterproofing the...
Recent Articles
Page 1 of 1




